Paris MoU Detention Report for Bulk Carrier MV Sea Bridge

The ship was banned in Italy in 2002. The banning was lifted in December 2007 and the vessel was on a voyage to Port of Szczecin in Poland. After lifting the ship from banning, she was due for a Mandatory Expanded Inspection (MEI). The Mandatory Expanded PSC PMoU Inspection was carried out on 19 December 2007 on partly discharged ship in Szczecin – Poland by two of our PSC Officers. After the inspection the ship was detained having among other 27 deficiencies identified.

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 1

More specifically the following were noticed:

  • In her Statutory Certificates some wrong entries, more specifically a not updated form IOPP Certificate and Oil Record book with improperly entries.
  • On the partly corroded deck heavily corroded and a holed hatch cover pontoons.
  • Perished, broken and holed tarpaulins used as a weather cover over hatch pontoons.
  • Beams and frames were heavily corroded, cracked and damaged.
  • During the abandon ship drill the crew were not familiar with the Muster List. The PS lifeboat was completely seized in its stowage position. Its launching devices were inoperative. The boat could not be moved.
  • Windlass completely corroded with a partial damaged foundation.
  • Greased moving parts were not found at all.
  • Mooring rollers seized, corroded: were not movable or greased.
  • Some of crew sanitary facilities were inoperative.

As a result a Ship Safety Management System Major Non Conformity was raised and the ship was detained. Due to the detention the following actions were taken:

  • Flag State Mongolia and the International Ship Classification in Singapore were informed immediately.
  • Relevant repairing was carried out.
  • Principal Surveyor of IS Class as well as the owner’s superintendent attended the ship.
  • A necessary ISM audit has also been carried out.

After completion of all necessary supplying and repairing, the ship was lifted from detention on the 4th of December 2007 heading to St. Petersburg – Russian Federation.

Photos taken during the inspection

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 2

Photo above: PS lifeboat launching devices seized; not movable

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 3

Photo above: Boat quick release mechanism to be repaired

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 4

Photo above: Corroded and cracked boat hook supports need to be repaired

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 5

Photo above: Hatch cover pontoons found corroded

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 6

Photo above: Hatch cover pontoons found cracked

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 7

Photo above: With manholes covers damaged and holed by corrosion

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 8

Photo above: Deck corroded and tarpaulins perished, damaged, hatch cover pontoons also corroded

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 9

Photo above: Bulwark stays, beams and frames corroded

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 10

Photo above: Bulwark stays, beams and frames corroded damaged

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 11

Photo above: Bulwark stays, beams and frames cracked

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 12

Photo above: Corroded, damaged forecastle under repairing for PSCO recommendation

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 13

Photo above: Mooring rollers seized, and corroded

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 14

Photo above: Inoperative windlass found with heavily corrosion and damaged foundation

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 15

Photo above: Windlass foundation and cracking

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 16

Photo above: Heavily corrosion

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 17

Photo above: Rust damages

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 18

Photo above: No greased windlass found

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 19

Photo above: Life raft cannot be used; no release unit provided

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 20

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 21

Photo above: Sanitary facilities inoperable

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 22

Photo above: Crew’s shower in a bad condition

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 23

Photo above: Corridor used as storage room

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 24

Photo above: Some of the electric equipment was not safe

2013.09.19 - Paris MoU Detention Report for Bulk Carrier MV Sea Bridge Figure 25

Photo above: In emergency pump room draining water release mechanism not marked

Source: Paris MoU

Comments

  1. PSC inspection, photo and description of my work 100%!
    Krzysztof G.Pomorski C/E

  2. Here are the documents inspected the ship m.v Sea Bridge:

Leave a Comment

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: